Marsh Lake Building Committee Meeting #13

December 13, 2004

Marsh Lake Fire Hall

 

Present:      Lea-Ann Dorval, Blair Corley, Wolf Schall, Lucy Skuba, Tiff Tasane, Susan Walton, John Streicker, Paul Sparling, Gordon Sinclair, Mike Frasher

 

Regrets:      Mike Larsen, Donna Larsen

 

13.0

Call to order:         7:03 pm

 

13.1

Agenda:      Accepted with addition of discussing showers during Schematic Report

 

13.2

Discussion re Building Committee group dynamics.

-         Concern expressed about our conduct.

-         Reminder given to meet / engage /interact with each other respectfully, to listen while other people are talking.

-         Should be no need for people to repeat themselves on points.

-         Recognition given that we are a diverse group and we’ve done a lot of good work as a group – often reaching consensus to date.

 

13.3

Discussion re construction costs.

-         Mike F. presented a two pager on budget scenarios (attached) to discuss the potential variability of a project cost estimate.

-         Schematic design phase estimate is +- 20%. As the design development stage progresses, this uncertainty will tighten.

-         Market uncertainties could be + 25% (e.g. prevailing conditions, inflation, etc.). There are inherent financial risks in the process. We need to be aware and do our best to ensure the tendering process follows our timeline.

-         Good to keep these thoughts in mind as we work on design decisions. Saving money is much easier to do at early stages in the process – later it becomes more difficult to find large savings.

-         John S. suggested that a version of this 2 pager accompany the proposed letter to Sport and Rec.

 

13.4

Discussion re Schematic Design Report

-         Gordon S. submitted final report on schematic design.

-         Mike F. walked us through the report.

-         Typos noted on p. 17 para 4. should read 2 AHU units (rather than 3) and para 5. should read AHU-2 (rather than AHU-3).

 

13.5

Discussion re showers

-         General show of hands around committee showed that we were interested in having showers in the community centre.

-         Good for hygiene. At the lake there is usefulness to have access to a shower for some residents.

-         Showers will only be available during open hours of centre – some concern if this will keep them useful?

-         If our librarian is a YTG employee, is a shower required?

-         Cleaning issue raised. Possibly coin operated – could offset some janitorial costs?

-         Is 1 male + 1 female shower enough?

-         Discussed the possibility of doing more with showers during a fitness room expansion. Should put thought into plumbing stubs now for that possibility.

-         Discussed the possibility of reworking the library into the admin space or the meeting room (room in NW corner). Realized we still need to know more about the rules / regulations of a library and how that might work.

-         Gordon S. stated that we could come back with suggestions re showers within 3 weeks with no impact to the timeline.

-         Building Committee reconfirmed, with consensus the building footprint as submitted (i.e. decisions regarding showers will not alter the building footprint).

 

13.6

Action:     John S. and Tiff T. to investigate the rules and regulations re the library and report to committee.

 

13.7

Discussion re ceiling height of gym / community hall / big room

-         Lucy S., John S. and Paul S. reported back on their investigation of other gyms:
Jack Hulland small gym = 35’ x 55’ x 17’
Jack Hulland big gym = 65’ x 100’ x 22’
Golden Horn gym = 60’ x 70’ x 22.5’ (19.5’ clear)

-         Lucy S. wrote letters to volleyball associations to get some informed opinion on the matter. One respondent said that a couple extra feet would make a difference, but that for recreational play people could probably make do. Also gave the suggestion that we could just let play continue if a ball hits the ceiling.

-         Mike F. noted that original 24’ came from having two floors. Current 18’ height was established by trying to maximize height with stock lumber (e.g. Gordon S. designed special truss system which would allow for central ducting)

-         Gordon S. gave some revised cost estimates having investigated further. Starting with 18’ as base, then +2’ = +$40K construction +10% O&M (approx.), or +6’ = +$80K construction + 30% O&M (approx).

-         Current 18’ design has a clean finish (i.e. no surface mount features).

-         Thanks to Lucy S., Paul S., John S. & Gordon S. for the additional work.

 

13.8

Decision:     Consensus on gym/hall height of 18’.

 

13.9

Decision:     Consensus that we recommend the Sinclair and Associates Ltd. Schematic Design Report Community Recreation Centre Option #7 December 13, 2004 to the Marsh Lake Community Society Board of Directors.

 

13.10

Action:     The committee expressed its thanks to Gordon S. for all his work.

 

13.11

Discussion re Malcolm’s report

-         John S. reported that Malcolm was away at the moment on personal matters.

-         Tiff T. stated that Malcolm is still hoping to submit his report soon (this calendar year?).

-         The committee noted that we still have not made any decisions or recommendations based on Malcolm’s report (for example the concept of having a bar still has not been debated in committee).

-         The committee recognizes that we could/should comment on Malcolm’s report, but it will ultimately be a decision for the Board.

 

13.12

Discussion re letter to Sport and Rec.

-         Current letter of agreement with Sport and Rec states that the community centre is “not to exceed $1.5M”

-         Tiff T. suggested submitting a letter to Sport and Rec that requests that we are designing a community centre “the target of which is $1.5M”.

 

13.13

Decision:     Tiff T. to draft letter as per comment above, circulate it to the committee for information and submit it to Sport & Rec.

 

13.14

Amendments:        6-Dec-04 minutes (Meeting #12)

-      12.5 remove clause “if/when demand/funding becomes available” from last point.

-      12.6 remove word substantial from first point.

-      12.6 change phrase “Windows in the gym: everyone…” to “Windows in the gym: most…” in last point.

-      12.9 change phrase “Rules state…” to “Gordon S. thought rules state…” in second last point.

 

13.15

Minutes:   6-Dec-04 minutes accepted as amended
27-Nov-04 minutes tabled

 

13.16

Adjourned:            9:25 pm


- For Committee Review & Discussion -

 

Examples of unit rate construction costs, and how they impact the overall project budget are detailed below:

 

The committee is nearing the conclusion of the schematic design process and has made a number of difficult choices with respect to the building size and complexity during this process. Prior to concluding the schematic design process I would like to revisit the schematic design budget for the benefit of the committee members.

 

Budgets produced during the schematic design stage are considered to be accurate within a range of approx. 20%. The budget typically is based on projects of similar magnitude and recent construction costs in the industry. The budget also allows for a design contingency to cover items that were not known, or included, within the design at this early stage. It is also common on construction projects to have the estimated costs of construction increase during the design stages. This is attributed to the process of design, which begins with a blank page or drawing and concludes with a very detailed set of drawings and specifications. The detailed drawings and specification provide both the consultants and contractors with specific information on the requirements of the project and in turn, the costs for the work. Therefore the accuracy of the design estimates should increase with the amount of design work completed, although at this early design stage there are still many unknown items that have to be worked out in the design process.

 

To facilitate the discussion on the estimated project costs I will use a “Unit Rate” cost for comparing various cost scenarios. The unit rate is used in lieu of providing detailed estimates at this stage of design to simplify the estimating process, and is due in part to the limited detailed design information that is available.

 

 

Scenario #1 ($2,000/m2 as per Sinclair Schematic Design & and FSC Report)

 

Building Area = 700 m2     Unit Cost = $2,000.00/m2 $1,400,000.00

Construction Contingency (Set Amount at $100,000)            100,000.00

Design and Administration Fees @ 10%        140,000.00

Furniture and Equipment (Set Amount at $50,000)                50,000.00

 

Total Projected Costs                  1,690,000.00                     

 

Scenario #2 ($2,000/m2 + 20% Upper Range of S.D. Estimate)

 

Building Area = 700 m2     Unit Cost = $2,400.00/m2 $1,680,000.00

Construction Contingency (Set Amount at $100,000)            100,000.00

Design and Administration Fees @ 10%        168,000.00

Furniture and Equipment (Set Amount at $50,000)                50,000.00

 

Total Projected Costs                  1,998,000.00                     

 

Scenario #3 ($2,000/m2 x1.25 for Market Conditions and Material Inflation)

 

Building Area = 700 m2     Unit Cost = $2,500.00/m2 $1,750,000.00

Construction Contingency (Set Amount at $100,000)            100,000.00

Design and Administration Fees @ 10%        175,000.00

Furniture and Equipment (Set Amount at $50,000)                50,000.00

 

Total Projected Costs                  2,075,000.00                     

 

 

Scenario #4 (Scenario #2 compounded with Scenario #3)

 

Building Area = 700 m2    Unit Cost = $2,400.00/m2x1.25 $2,100,000.00

Construction Contingency (Set Amount at $100,000)            100,000.00

Design and Administration Fees @ 10%        210,000.00

Furniture and Equipment (Set Amount at $50,000)                50,000.00

 

Total Projected Costs                  2,460,000.00                     

 

Scenario #5 ($2,000/m2 – 20% Lower Range of S.D. Estimate)

 

Building Area = 700 m2     Unit Cost = $1,600.00/m2 $1,120,000.00

Construction Contingency (Set Amount at $100,000)            100,000.00

Design and Administration Fees @ 10%        140,000.00

Furniture and Equipment (Set Amount at $50,000)                50,000.00

 

Total Projected Costs                  1,410,000.00                     

 

 

As can be seen by the above budget projections the combination of increases in the costs as the design progresses coupled with market conditions can have a significant impact on the cost of construction. Based on the current conditions being experienced in the Yukon and most other jurisdictions in Canada, it is a reasonable expectation that the project will require careful consideration of design features throughout all stages of the design to increase the chances of delivering this project on budget. The design budget currently established will be reviewed and updated as the design progresses, and the committee will be challenged to make decisions which will maintain the core features and components of the building while keeping the project in balance with the budget.

 

The above budget projections will continue to be refined as the design progresses. However, as can be seen in the above scenarios, there is considerable risk and challenges ahead, to deliver a facility which meets both the communities needs and the remain within the construction/project budget.